Receive inspection and obtain certificate of completion from Working Commission
: Working Commission
Agency
After the inspection, an act of acceptance is drafted and endorsed by all members in no more than
5 working days.
The Working Commission will inspect, among other things:
• The compliance of the building and construction works with the requirements on labor protection,
fire safety, environment protection, and its prevention of human-caused emergency situations, and
so forth
• The separate constructions and units of the warehouse
If its findings are favorable, the commission then accepts the construction for subsequent
presentation to the State Acceptance Board.
The Working Commission issues the following:
• The certificate of allowable concentration of radon in the completed constructions
• The certificate of acceptance of the temporary buildings and constructions
• The certificate of readiness of the construction for presentation to the State Acceptance Board
21 days
no charge
16
Request and obtain certificate of acceptance from the Tashkent City Hokimat
: Hokimat
Agency
The Hokim (the head of the city government) decides whether to approve the Working
Commission’s act of acceptance within 2 days. However, in practice, this takes longer. There is no
fee involved. The decision of Hokim is further needed for registering the building with the cadastre
authorities.
BuildCo should submit to the State Acceptance Board, among other documents, the following
documents:
• The certificate on elimination of defects brought to light by the Working Commission
• The approved project and estimate documentation
• The list of project and research organizations that participated in construction
• Other relevant documents
14 days
no charge
17
Register the new construction with the cadastre
: Cadastre
Agency
BuildCo must register the new construction with the real estate cadastre of the relevant district of
the city of Tashkent. The registration takes around 2 weeks in Tashkent and costs 50% of MMW
for legal entities.
30 days
UZS 101,365

Yüklə 1,75 Mb.

Dostları ilə paylaş:
1   ...   12   13   14   15   16   17   18   19   ...   64




Verilənlər bazası müəlliflik hüququ ilə müdafiə olunur ©www.genderi.org 2024
rəhbərliyinə müraciət

    Ana səhifə